MONROE - The street department will be sealing the stamped concrete around the Square during the weeks of Aug. 13, Aug. 20 and Aug. 27.
The department will begin with the crosswalks at mid-block the week of Aug. 13. After the crosswalks are completed, they will continue with traffic, doing one side at a time.
The concrete must be flushed with water and then completely dried before the sealant can be applied. The process is dependent on weather conditions and may take several hours.
During this time, parking stalls with stamped concrete must remain closed until sealant is totally dry.
For more information, contact the street department at (608) 329-2490 or the engineering department at (608) 329-2532.
The department will begin with the crosswalks at mid-block the week of Aug. 13. After the crosswalks are completed, they will continue with traffic, doing one side at a time.
The concrete must be flushed with water and then completely dried before the sealant can be applied. The process is dependent on weather conditions and may take several hours.
During this time, parking stalls with stamped concrete must remain closed until sealant is totally dry.
For more information, contact the street department at (608) 329-2490 or the engineering department at (608) 329-2532.