8th/9th Street project begins
Placeholder Image
From Al Gerber Engineering Supervisor, City of Monroe During the week of March 14, Dane County Contracting installed 300 feet of 8-inch water line along the south side of 8th Street from Wisconsin 69 to 8th Avenue. Next week, Dane County Contracting will continue with the remaining 300 feet of water main on 8th Street through 8th Avenue to the bridge. Then they will move the water main installatation to 10th Avenue and 8th Street to complete the installation of a new main crossing 8th Street by the Highlander Mall.