8th Street Update: 8th Street work progresses, night closures to continue
Placeholder Image
Progress continued this week with contractors focusing on the center construction zone between 2nd Avenue and Wisconsin 69. Contractors worked multiple nights removing the existing pavement and placing new stone while deteriorated sanitary manholes were removed and replaced. During the day, lining crews cleaned and televised underground sanitary lines in preparation for lining and concrete crews poured new curb and concrete pavement near the intersection of Wis. 69.